Robert Blue6:05
Thank you, Steven. I'll begin with safety on slide five. Our employee OSHA injury recordable rate for the first quarter of the year was 0.42, which remains well below the industry average. Safety is our first core value, and we're continuing our efforts to drive to zero workplace injuries. I'll start our business updates with the Coastal Virginia Offshore Wind project on slide six. The project is now over 75% complete. And as Steven mentioned, in March, we achieved a very significant milestone with the delivery of much-needed power to customers. General fabrication and installation continue to proceed very well. We've now completed installation of all 176 transition pieces that connect the monopile foundations to the turbine towers. All three substations are installed, and commissioning is proceeding as planned. Deepwater export cables are installed, and array cable installation is on track. All of the remaining cabling is now fabricated, and the majority is landed in Virginia. And we're making excellent progress on turbine fabrication. Over 86% of towers, approximately 69% of nacelles, and about 45% of blades have been fabricated. This progress tracks well relative to our schedule. With regard to wind turbine generators, we're seeing materially positive improvements in installation cadence as shown on slide seven. We affirm our previously communicated timeline for project completion, with the majority of turbines expected to be placed in service by the end of 2026, and the remainder in early 2027 prior to the end of June. As of this morning, we've completed nine turbines. During the first quarter, we successfully calibrated our procedures and equipment and navigated winter weather. Since then, we've been able to ramp the installation rate markedly, including averaging approximately two days per installation for our last four turbines, which supports our existing timeline for project completion. We continue to seek to optimize the process resulting in improved installation times. In addition, we're moving into better weather windows for the next several months. Please note the current project budget includes turbine installation schedule contingency for weather delays through July 2027 as needed, including Charybdis charter costs. I'll also reiterate our general rule of thumb. If the project extends beyond July 2027, we estimate that each additional quarter to complete turbine installation would add between 150 million and 200 million dollars to the project costs, a portion of which would be allocated to our financing partner. We'll continue to include data from additional installation iterations in our quarterly updates. As shown on slide eight, the project budget now stands at 11.4 billion dollars, which is approximately 100 million lower than our last update. We've updated the budget to reflect changes in tariff assumptions as a result of recent judicial and administrative actions. Unused contingency stands at 123 million. Looking forward on project costs, we're monitoring the potential of two recent events. First, certain regional transmission projects were captured in both the PJM transition cycle, which resulted in network upgrade costs allocated to CVOW, and the subsequent broader RTEP award package. As a result, we would expect the overall network upgrade costs allocated via the PJM transition cycle across all generation queue projects, including CVOW, to be reassessed and reduced. Second, recently updated steel and aluminum tariffs, which are pending additional information from suppliers and guidance from the applicable agencies. As shown on slide nine, the project's cost sharing and risk sharing continue to work as intended to protect customers and shareholders with no change to either LCOE or customer bill impacts. CVOW remains one of the most affordable sources of energy for our customers. Our updated analysis indicates that the project is expected to generate fuel savings of approximately $5 billion for customers during the project's first 10 years of operations. Taking a step back, an all-of-the-above approach to energy supply, including CVOW, is critical to ensuring continued reliability amidst real-time growing demand in our service areas. Building new energy generation is a core competency of ours, as demonstrated in recent years with our successful development of thousands of megawatts of renewable generation, as well as combined cycle plants in Greensville, Brunswick, and Warren County. We continue to advance the development of new generation capacity consistent with our update last quarter. In addition to producing much-needed energy for our customers, these projects will be an economic benefit for Virginia, generating thousands of new jobs, billions of dollars of economic investment, and meaningful local tax revenue. Turning to slide 10, I'll reiterate that we view customer affordability as central to our public service obligation, and accordingly, we have a long record of maintaining competitive rates, which continue to compare favorably to the national average. Even while executing one of the largest regulated investment programs in the sector, we expect our customer bills will continue to grow at rates comparable to inflation over the long term, demonstrating disciplined capital deployment and our regulatory construct working as intended. We recognize, though, that customers are feeling the pressure of higher costs for housing, groceries, and other essentials, including their electric bill. We have a number of programs designed to help our customers manage their bills, including budget billing, energy savings programs, and financial assistance programs such as EnergyShare. Late last year, we also launched a new online platform to put all our programs in one place, so customers can more easily find the best options to meet their needs. In addition to providing tools to help manage payments, we're also working to ensure fair and reasonable rates. For instance, the commission approved our recently proposed large load provisions in the 2025 biennial to ensure that our smaller customers aren't at risk of subsidizing our largest customer classes, nor be left with stranded costs. We also plan to pursue fuel securitization in Virginia for unrecovered fuel costs to minimize the rate impact on customers. We work continuously to improve the efficiency of our operations, while meeting high customer service standards and reliability needs. In recent years, we've driven out costs through improved processes, innovative use of technology, and other best practice initiatives. On the technology front, we're focused on implementing technology initiatives that accelerate our mission, and we've recently deployed a range of AI tools. For example, in our contact center, AI enables clear visibility into customer needs at scale and real-time insight into customer sentiment, allowing us to respond with greater precision and efficiency. Looking ahead, we're intently focused on ensuring our service isn't just reliable, but that it remains affordable as well. Now, I'll turn to other business updates as shown on slide 11. In South Carolina, DESC's electric rate case continues to progress. Staff and other interveners filed their testimony on March 31st. We filed our rebuttal testimony on April 21st and expect surrebuttal testimony on May 5th, consistent with the procedural schedule. Hearings are scheduled for mid-May, and we expect a decision in late June with rates effective in July. Yesterday, we filed an electric rate case application and testimony for Dominion Energy North Carolina to support the approximately $400 million investment placed in service by the company attributed to North Carolina since the 2024 rate case and ensure that we can continue to provide safe, reliable, and cost-effective service to our North Carolina customers. We expect a decision in February 2027 with interim rates effective December 26th subject to true up and finalization in March 2027. Recall DENC represents about 4% of the company's investment base. Finally, on Millstone. I'll start by noting Governor Lamont's comments last week highlighting the hundreds of millions of dollars that the current Millstone contract has saved customers and which is now resulting in a material customer bill reduction in Connecticut. In March, the facility submitted its bid in the Connecticut Department of Energy and Environmental Protection's zero carbon energy request for proposals. Per DEEP's published schedule, solicitation decisions are expected in the second quarter with negotiations with the local state utilities to begin in the third quarter. Contracts will be submitted to the Connecticut Public Utilities Regulatory Authority for approval thereafter. The timeline for which is up to 180 days. In addition to state-sponsored procurement, we continue to evaluate the prospect of supporting incremental data center activity as well. We remain focused on achieving a constructive outcome for the facility and will continue to provide updates as things develop. With that, let me summarize our remarks on slide 12 by reiterating where Steven began the call with a focus on our top three priorities: consistently achieving our financial commitments, continued on-time achievement of major construction milestones for the Coastal Virginia Offshore Wind project, and achieving constructive regulatory outcomes that demonstrate our ability to work cooperatively with regulators and stakeholders to deliver results that benefit both customers and shareholders. We're 100% focused on execution. We remain committed to delivering reliable, affordable, and increasingly clean power for our customers. With that, we're ready to take your questions.